Illustrative image – not actual.The south-bound arm of this Rs 22 crore flyover was thrown open to public in June, 2014.
With the north-bound arm open, the Kherwadi flyover will have three lanes each, for north and south-bound commuters. The 580 mtr flyover is the last link in the Western Express Highway.
The Kherwadi flyover is one of the fastest projects to be implemented. The north-bound arm, the construction of which started in October 2014, was completed in six months, while the south-bound arm was completed in about seven months.
The advantage in the construction of the north-bound arm was that the precast girders (concrete blocks) for four of the five spans had already been casted at the Wadala casting yard. This arm comprises a total of 25 precast girders, out of which 20 girders were ready prior to the start of the project.