Hyderabad’s Buddha Purnima Project to be completed in 2015Illustrative image – not actual.
Hyderabad’s Buddha Purnima lake project, which was taken up for the improvement of Hussainsagar lake and the catchment area, is likely to be completed in March 2015.


The lake project is being implemented by the Hyderabad Metropolitan Development Authority (HMDA) with the Official Development Assistance loan of Rs 370 crore from Japan International Cooperation Agency (JICA), and another Rs 60 crore from the state's share in the year 2006-07.


HMDA has so far used Rs 245 crore of the total loan amount for construction and renovation of sewerage facilities, while the remaining Rs 125 crore is being used for additional interception and diversion structures on the Necklace Road.


The projects around the Hussainsagar lake taken up with the Rs 245 crore of JICA funds are:


1. Three Sewage Treatment Plants of 30 MLD at Picket nala; 20 MLD at Balkapur nala; and five MLD at Rangadhamini lake, constructed to treat water with permissible limits of nutrients
2. Interception and diversion structures at Fatehnagar, Prakashnagar and Necklace Road on Kukatpally, Picket and Balkapur nalas
3. 1,600 mm diameter ring main (connecting structure) from Kukatpally nala to Buddha Bhavan
4. 1,400 mm diameter ring main at Balanagar trunk main in Kukatpally catchment area
5. Trunk sewer under execution by the Water Board in four packages. This project is to be completed by March 2015.


As per the JICA loan disbursement, the lake project has to be completed by July 2016. However, most of the work is expected to be completed by March 2015.

 

More Project Info:
Hussain Sagar Lake (Hyderabad) Project