Ground breaking ceremony for Solar PV System at RourkelaIllustrative image – not actual.

The ground breaking ceremony for a one MW Solar PV Power Generation System was performed at Rourkela Steel Plant (RSP) on 10 February, 2015.


The Rs 6.37 crore solar power plant will be the first of its kind and scale in SAIL. The power generation system will generate solar-electrical power from 3,465 solar photovoltaic panels installed over an area of 4.7 acre in the plant premises.


Rays Power Infra are the contractors for setting up the plant. The project is being executed by Power Distribution Department of RSP, and Canyon Consultancy are the consultants.


The solar installation is scheduled to start power generation by June 15, 2015. The plant is expected to generate 16,48,000 kWH of electrical energy in its first year of operation and the design life of the plant is twenty years.


15 string inverters of 60 kW capacity each will convert the DC power generated by the solar panels to 415 VAC power. This, in turn, will be stepped up to 6.6 kV through one 1,600 kVA transformer.


The power generation system shall be connected to the RSP power system at Administration substation, located at an approximate distance of 1.2 km from the project site.


Power generated from the installation shall be used to meet the Renewable Power Obligation (RPO) prescribed by the Orissa Electricity Regulatory Commission.

 