Finolex to augment capacity at three plants in phasesIllustrative image – not actual.

Finolex plans to increase the capacity of its three current pipe plants in a phased manner. It has set up its first warehouse in Odisha for expansion into northern and eastern markets.

 

In the next three years, the company envisages setting up 10 such warehouses across India. With the brownfield expansion at its units at Pune, Ratnagiri, and Masar, the company will add 30,000 tonne a year capacity in the future.

 

The increment capex of Rs 90 crore will raise the annual capacity to 3.2 lakh tonne. Finolex expects to grow at 15-20 per cent a year, with a rise from its pipes revenue.

 