Illustrative image – not actual.The balance 90 MW (3 x 30 MW) will be commissioned in phases, in the coming months.
The 120 MW coal-fired power plant will meet the power requirements of Essar Steel's 12 million tpa integrated palletisation facility in Odisha. The Paradip facility consists of a palletisation plant at Paradip and a beneficiation plant at Dabuna, connected through a 253 km slurry pipeline.
The 220 kV transmission line from the plant switchyard to the main receiving substation (MRSS) of the steel plant has already been commissioned for power evacuation. The related infrastructure like port facility for coal handling has already been set up by Essar Ports.
As per the PPA agreement, the fuel and water supply responsibility rests with the client (Essar Steel).
More Project Info:
Coal Based Power (Paradip) Project