Adilabad power project Phase-II launchedIllustrative image – not actual.
Singareni Collieries Company (SCCL), has begun work on Phase-II of its 2x600 MW coal-fired project at Adilabad, which will add an additional 600 MW. This project marks the diversification of the company into the power generation sector.

 

The foundation of Phase-II, worth Rs 3,570 crore, was laid on 3 March. The project is likely to be ready in 30 months.

 

Phase-I, comprising the 2x600 MW plant, is under construction. The BTG package is being executed by BHEL; the balance of the plant by McNelly Bharat Engg and Consortium partners.

 

The company has assured to increase resources to meet the synchronisation schedule of the first unit in November 2015 and the second in December 2015.

 

Besides, SCCL is also building another 1,200 MW project.

 